PERT Three-Point Estimates: Expected Duration, Standard Deviation, and Confidence
October 29, 2026
Single-point estimates hide uncertainty. The PERT method asks for three estimates for each task: optimistic (O), most likely (M), and pessimistic (P). The expected duration is the weighted average TE = (O + 4M + P) ÷ 6, and the standard deviation is approximately SD = (P − O) ÷ 6.
Task A: O = 2, M = 4, P = 12 days gives TE = (2 + 16 + 12) ÷ 6 = 5.0 days and SD = 10 ÷ 6 = 1.67. Task B: O = 3, M = 5, P = 7 gives TE = 5.0 and SD = 0.67. Task C: O = 4, M = 6, P = 14 gives TE = 7.0 and SD = 1.67.
Skip the math and get your answer instantly:
Open the Average Calculator →Combining Tasks in Sequence
For tasks done one after another, expected durations add: 5 + 5 + 7 = 17 days. Variances (SD squared) also add: 2.78 + 0.44 + 2.78 = 6.0, so the path's SD is √6 = 2.45 days. Note that you add variances, not standard deviations; adding the SDs (4.0) would overstate the spread. Uncertainty adds less than linearly because delays in one task tend to be offset by early finishes in another (assuming independence).
A normal approximation gives schedule probabilities: the chance of finishing within 17 days is about 50%, within 19.4 days (17 + 1 SD) about 84%, within 21.0 days (17 + 1.645 SD) about 95%, and within 24.3 days (17 + 3 SD) about 99.7%.
| Task | O / M / P | Expected (days) | SD |
|---|---|---|---|
| A | 2 / 4 / 12 | 5.0 | 1.67 |
| B | 3 / 5 / 7 | 5.0 | 0.67 |
| C | 4 / 6 / 14 | 7.0 | 1.67 |
| Path total | 17.0 | 2.45 |
Setting a Commitment
Quote a date at the confidence you need: 17 days if you accept a coin-flip chance of delay, 19.5 days for about 84%, 21 days for 95%. Compare this with the sum of the most likely values (4 + 5 + 6 = 15 days), which is optimistic: there is only about a 20% chance of finishing in 15 days. Because the pessimistic estimates are skewed, the expected value (17) exceeds the sum of the most likely (15). That is a common source of overrun when only the most likely values are used.
Parallel Paths and Limits
For a project with parallel paths, the critical path (the longest) drives the schedule, but the chance of finishing on time is lower than for any single path, because any of them might be late. Estimates are subjective and often biased toward optimism; gather estimates from the people doing the work and review them against past projects. The beta distribution assumed by PERT is an approximation, and for large projects, simulation provides a better picture.
Frequently Asked Questions
What is the PERT formula?
TE = (O + 4M + P) ÷ 6.
How do I find the standard deviation of a task?
(P − O) ÷ 6.
How do I combine uncertainty across tasks?
Add the variances and take the square root.
What confidence does mean + 1.645 SD give?
About 95%.
Why not just add the most likely values?
Because skewed pessimistic risks make it too optimistic.